ASTM E 2516 : 2011

Superseded

Superseded

A superseded Standard is one, which is fully replaced by another Standard, which is a new edition of the same Standard.

View Superseded by

Standard Classification for Cost Estimate Classification System

Available format(s)

PDF

Language(s)

English

Published date

01-04-2011

Superseded date

20-05-2024

£57.74
Excluding VAT

Committee
E 06
DocumentType
Standard
Pages
7
PublisherName
American Society for Testing and Materials
Status
Superseded
SupersededBy
Supersedes

1.1 This classification provides a generic classification system for cost estimates and provides guidelines for applying the classification to cost estimates.

1.2 This classification maps the phases and stages of cost estimating to a generic maturity and quality matrix, keyed to a degre of project definition, that can be applied across a wide variety of industries.

1.3 The Cost Estimate Classification System has been developed in a way that:

1.3.1 provides a common understanding of the concepts involved with classifying cost estimates;

1.3.2 defines and correlates the major characteristics used in classifying cost estimates, and;

1.3.3 uses the degree of project definition as the primary characteristic used to categorize estimate classes.

ASTM E 3008/E3008M : 2016 Standard Classification for Transportation Surface Elements—UNIFORMAT II
ASTM E 2103/E2103M : 2013 Standard Classification for Bridge Elements—UNIFORMAT II

ASTM E 1804 : 2016 Standard Practice for Performing and Reporting Cost Analysis During the Design Phase of a Project
ASTM E 1804 : 2007 Standard Practice for Performing and Reporting Cost Analysis During the Design Phase of a Project
ASTM E 1804 : 2012 Standard Practice for Performing and Reporting Cost Analysis During the Design Phase of a Project
ASTM E 1804 : 1996 Standard Practice for Performing and Reporting Cost Analysis During the Design Phase of a Project
ASTM E 1804 : 2002 Standard Practice for Performing and Reporting Cost Analysis During the Design Phase of a Project