BS EN 50341-2-8:2017
Current
The latest, up-to-date edition.
Overhead electrical lines exceeding AC 1 kV National Normative Aspects (NNA) for FRANCE (based on EN 50341-1:2012)
Hardcopy , PDF
English
31-12-2017
European foreword
0 Introduction
1 Scope
2 Normative references, definitions and symbols
3 Basis of design
4 Actions on lines
5 Electrical requirements
6 Earthing systems
7 Supports
8 Foundations
9 Conductors and earth wires
10 Insulators
11 Hardware
12 Quality assurance, checks and taking-over
Annex J (normative) - Angles in lattice steel towers
Annex K (normative) - Steel poles
Annex M (informative) - Geotechnical and structural
design of foundations
Pertains to new overhead lines as defined in 1.1/FR.2 'Definition of a new overhead line'.
Committee |
PEL/11
|
DevelopmentNote |
Supersedes BS EN 50423-3 & BS EN 50341-3 which remains current. (01/2018)
|
DocumentType |
Standard
|
Pages |
72
|
PublisherName |
British Standards Institution
|
Status |
Current
|
Supersedes |
(ncpt) FR.1 Scope of Part 1 and Part 2-8 Part 1 and the present Part 2-8 apply to new overhead lines as defined in 1.1/FR.2 \'Definition of a new overhead line\'. (ncpt) FR.2 Definition of a new overhead line A new overhead line denotes any new overhead electrical line exceeding AC 1 kV built on new foundations and: - flanked by two substations or two terminal towers preceding said substations. or - flanked by a substation or a terminal tower at one end and in a branch situation (including branch tower) or tapping situation at the other end. (ncpt) FR.3 Application to existing overhead lines This standard does not apply to existing overhead lines exceeding AC 1 kV in France. (ncpt) FR.4 Application to overhead lines for which technical studies are underway Any decision to apply the requirements of the present standard to new overhead line projects for which technical studies are underway shall be stipulated in the Project Specification. (ncpt) FR.5 Application to overhead lines under construction The requirements of the present standard do not apply to overhead lines under construction. (ncpt) FR.1 Application to radio telecommunication equipment Part 1 and Part 2-8 apply to radio telecommunication equipment mounted on the towers of new overhead lines, particularly with respect to wind and ice assumptions. Radio equipment shall be arranged on the support so that it can be accessed and operations performed in accordance with safety regulations.
Standards | Relationship |
EN 50341-2-8:2017 | Identical |
NFC 11 201 : 1996 AMD 1 2004 | PUBLIC ELECTRICAL POWER SYSTEMS |
NFP 94 262 : 2012 | GEOTECHNICAL DESIGN - FOUNDATIONS - DEEP FOUNDATIONS |
UTEC 11 001 : 2001 | NETWORKS - STATUTORY REGULATIONS FOR ELECTRICAL POWER DISTRIBUTION |
NF EN 61672-1 : 2014 | ELECTROACOUSTICS - SOUND LEVEL METERS - PART 1: SPECIFICATIONS |
NFS 31 010 : 1996 AMD 2 2013 | ACOUSTICS - ENVIRONMENTAL NOISE CHARACTERIZATION AND MEASUREMENT - SPECIAL MEASURING METHODS |
NF EN 50540 : 2011 | CONDUCTORS FOR OVERHEAD LINES - ALUMINIUM CONDUCTORS STEEL SUPPORTED (ACSS) |
NFP 94 261 : 2013 AMD 1 2017 | JUSTIFICATION OF GEOTECHNICAL WORK - NATIONAL APPLICATION STANDARDS FOR THE IMPLEMENTATION OF EUROCODE 7 - SHALLOW FOUNDATIONS |
NFC 18 510 : 2012 | OPERATIONS ON ELECTRICAL NETWORK AND INSTALLATIONS AND IN AN ELECTRICAL ENVIRONMENT - ELECTRICAL RISK PREVENTION |
Access your standards online with a subscription
Features
-
Simple online access to standards, technical information and regulations.
-
Critical updates of standards and customisable alerts and notifications.
-
Multi-user online standards collection: secure, flexible and cost effective.